Door installer came out. The wrong door and handleset/deadlock was ordered... ugh... They're installing it for now and it'll have to be switched out later. Hopefully the water is at least getting stopped at this point.
It does make sense. The first step was tearing out the old door's threshold, frame, jamb, etc. They had to install something to keep weather and thieves out. The door dimensions won't change, so all they'll have to change out is the slab. It won't cost me any money or time so it's ultimately not a big deal on my end, just one more thing in a cavalcade of errors.Why would they install the door if it is going to be replaced? Doesn't this involve cutting holes in the door making it so that it can't be returned? He would also be doing the work twice. It doesn't make a lot of cents!
It does make sense. The first step was tearing out the old door's threshold, frame, jamb, etc. They had to install something to keep weather and thieves out. The door dimensions won't change, so all they'll have to change out is the slab. It won't cost me any money or time so it's ultimately not a big deal on my end, just one more thing in a cavalcade of errors.
These are fiberglass doors, so the handset and deadbolt holes are pre-fabricated into the door slab.
On my end this is all in the category of "you (contractor) should have brought the correct door in the first place" as opposed to being a concern for me. The only difference was the type of glazing. I specified a frosted/satin etched glass and what arrived was clear. That doesn't work for me when it provides a window into a space full of expensive gear daring thieves to do what they do. These guys do a ton of work, so I'm sure they'll be able to re-use the door either way.I didn't realize that handset and deadbold holes were already machined. Still, it's going to be a used door once screws go into it. Perhaps it simply goes back into the installers inventory.
...and there's still lots of building left to go wrong! hahaThis is the mother of all threads...
Two schmucks in fact! There was the first one who did the intake of all my information, and then the second who was the account manager. It took the underwriter (a third person) to kick the aforementioned two schmucks into line.Sorry you got a schmuck
A quick three-part update;
1. The new door is holding back water brilliantly. Everything has been bone dry inside the studio since the install. With that sorted out I'm confident about getting back to work. I'll be finishing up the upper "triangle of the partition wall framing as well as completing the insulation. With those two items finished I'll be able to get my City of Seattle STFI permit closed-out. Now I just need to find the motivation to get that done.
2. The contractor is installing the correct door and hardware on Friday 4/28. Should be a simple swap and then programming the door code. After that I'll be able to have my painter come out to clean everything up, caulk the trim, and re-paint areas marred by the removal and replacement of the door. Lastly the door logo can be replaced.
3. Unfortunately it can't all be good news. The funding source to finish out the remainder of the work fell through. The lender's underwriter backed out at the last minute. The underwriter said this to me: "Your debt to income ratio is good, your income level is good, and the appraisal on your home was good. You're basically the ideal customer for us." There was then a long and uncomfortable pause because I could feel a "but" statement about to happen... and then it did... "but we're not going to be able to finalize this loan for you because your wife operates a business out of the home. We do not provide loans on properties that are mixed use." The kicker to this was that I had multiple conversations with the lender about my wife's business, whether or not that would be a problem (they said it would not be a problem), if it would affect the appraisal (it did not), the fact that my wife's business pays us rent which should be viewed as a benefit to my debt to income ratio, and lastly what documentation I would need to gather to disclose everything (they told me there wasn't anything required). The lender had repeatedly said that it would not be a problem. The underwriter apologized profusely and ultimately said that when I disclosed the business they should have stopped the process immediately since it's against policy to lend on properties that are mixed use. Evidently they have zero wiggle room on this. So with that in mind I'll be shopping for new lenders next week. With this project I've learned that delays are far preferable to taking steps backward, and this is simply a delay.