Construction sequence from this point on:
- GG sealant among all corners (walls, floors, ceilings)
- Drywall (mud and tape will be done by a contractor while other items are finished)
- HVAC (once mud and tape is finished)
- Final electrical (once mud and tape is finished and HVAC is hung)
- Mini split refrigerant vacuum and seal check (done by a contractor)
- Sound door
- Flooring underlayment
- Flooring
- Trim
- Paint
- Vestibule storage shelving
- Acoustic treatments (including rug at the mix desk)
- Fixed gear installation (rack, rack gear, mix desk, raven, computer, etc.)
- Furniture (i.e. one mix chair and a couple of stools for performers)
- Instrument wall hangers
- Instruments, cases, etc.
I'm sure I've forgotten something, but that's the bulk of it.