Construction sequence (ideally, assuming the electrical is done) from this point on:So once the drywall is done, what's the next layer going to be for the interior?
- Drywall (mud and tape will be done by a contractor while other items are finished)
- HVAC (once mud and tape is finished)
- Final electrical (once mud and tape is finished)
- Mini split refrigerant vacuum and seal check (done by a contractor)
- Sound door
- Flooring underlayment
- Flooring
- Trim
- Paint
- Vestibule storage shelving
- Acoustic treatments (including rug at the mix desk)
- Fixed gear installation (rack, rack gear, mix desk, raven, computer, etc.)
- Furniture (i.e. one mix chair and a couple of stools for performers)
- Instrument wall hangers
- Instruments, cases, etc.